Renovation of runway 07L/25R at Brussels Airport completed this weekend

General

The renovation works on runway 07L/25R at Brussels Airport and the final tests will be completed on the 23rd of August at 6 am, at which time the runway will be taken in use again. The contractors worked day and night, 7 days a week, to limit the duration of the runway closure and the impact of these works. Because of the corona crisis, this happened in a period with much less air traffic than usual. The thorough renovation of this runway was necessary to guarantee the safety of air traffic in the future.

The renovation works of the main runway of Brussels Airport, runway 07L/25R, which started on 13 July, will be completed on the 23rd of August. This means that the runway can be put back into service as planned. Thanks to good preparation together with all stakeholders, the hard work of all contractors and the favourable weather conditions at the important moments the works were always on schedule. In total, more than 100,000 hours of work were performed in 6 weeks by around 400 people per day. In total, about 1000 people have worked on this project. Thanks to this renovation, the life span of the runway is extended by at least 15 years.

The work carried out on the runway was very extensive. The top layers of asphalt were milled and replaced over almost the entire surface of the runway (3.3km by 60m). The lighting system of the runway, including all cabling, was replaced. In places where this was not yet the case, the lighting was replaced by energy efficient LED lighting. The drainage system was also renovated with new channel drains and sewage pipes.

Other works were also carried out on the cabling of the data network and the airfield light poles, as well as lawn repairs.

After the last security tests the renewed runway 07L/25R will be reopened at 6 am on Sunday 23 August. From then on, we go back to the preferential runway use as determined by the federal government.

Have a look behind the scenes of these works in this video:

Key figures


Asphalt layers

  • 270,000 m² of asphalt (± 40 football pitches), i.e. 70,000 tonnes manufactured in 3 asphalt plants
  • At peak times: 8,000 tons placed in 12 hours with 30 pavers and 100 trucks on the runway

Markings

  • 25,000 litres of paint

Lighting system

  • 2,000 runway and taxiway lights
  • 290 transformer pits
  • 320 km of cabling
  • 31 km of saw cuts
  • 10 km of trenches

Drainage

  • 7,4 km of channel drains
  • 1.4 km of new sewage pipes

Project management

  • 35 people to manage the site (contractors and Brussels Airport Company)
  • 15,000 hours of preparation (contractors and Brussels Airport Company)

Contractors

  • Infrastructure works: Willemen Infra NV
  • Lighting system: Mobix Stevens NV

Related articles

Brussels Airport and skeyes begin demonstration flights with steeper and innovative approach trajectories

General

Brussels Airport and air navigation service provider (ANSP) skeyes will commence demonstration flights as part of the HERON project from 1st October. The aim of these flights is to assess whether landings with a steeper approach than usual could offer benefits in terms of reducing noise impact for surrounding communities, as well as lowering CO2 emissions and fuel consumption.

Read more

Short maintenance works on 25R/07L

General

At Brussels Airport, all runways and taxiways are continuously inspected by the relevant departments to continue to guarantee the safety of the passengers and the operations.

Read more

ILS runway 19 out of service from 24/06/2024 to 06/07/2024

General

With the renewal of the ILS of runway 19 now in the final stage, skeyes needs to perform a series of updates on the installation.

Read more
icon_info Plane departing Group 7 Created with Sketch. Icon triangle warning Icon triangle left Icon triangle right Icon close Icon triangle warning Questionmark Reason meteo Reason obstacles Reason unplanned Reason planned maintenance Reason capacity exceeded Reason unavailable (non-availability) Reason special activities Reason other Search Arrow right