Work on taxiway Z completed 1 day ahead of schedule

General

The two upper asphalt layers of taxiway Z (behind aprons 40 and 4, near the Brussels Airlines and TUI fly hangars) were demolished and replaced. We are talking about a surface area of 50,000m².

New sewers were installed over a length of 710 meters and the taxiway lights were replaced with LED lamps. 

Today, the markings were completed. 

Taxiway Z is now operational again, one day ahead of schedule. 

Related articles

Brussels Airport and skeyes begin demonstration flights with steeper and innovative approach trajectories

General

Brussels Airport and air navigation service provider (ANSP) skeyes will commence demonstration flights as part of the HERON project from 1st October. The aim of these flights is to assess whether landings with a steeper approach than usual could offer benefits in terms of reducing noise impact for surrounding communities, as well as lowering CO2 emissions and fuel consumption.

Read more

Short maintenance works on 25R/07L

General

At Brussels Airport, all runways and taxiways are continuously inspected by the relevant departments to continue to guarantee the safety of the passengers and the operations.

Read more

ILS runway 19 out of service from 24/06/2024 to 06/07/2024

General

With the renewal of the ILS of runway 19 now in the final stage, skeyes needs to perform a series of updates on the installation.

Read more
icon_info Plane departing Group 7 Created with Sketch. Icon triangle warning Icon triangle left Icon triangle right Icon close Icon triangle warning Questionmark Reason meteo Reason obstacles Reason unplanned Reason planned maintenance Reason capacity exceeded Reason unavailable (non-availability) Reason special activities Reason other Search Arrow right