Renovation works on runway 01/19

Works

To maintain its runways in good condition, Brussels Airport will carry out renovation works on runway 01/19. The works are necessary to continue to guarantee safe air traffic in the future. To allow for these works, the runway will be completely closed to air traffic from 7 August to 1 September 2024.  

Following a thorough analysis, Brussels Airport has decided to renovate the top layer of the asphalt of runway 01/19. The actual work will be carried out from 7 August to 1 September 2024 and is scheduled during the day between 5 a.m. and 11 p.m. The full length of runway 01/19 will be resurfaced, except where it intersects with runways 25R/07L and 25L/07R.  Locally, Brussels Airport will also replace the first underlayer, lay new cabling and install new gutters to improve runway drainage.

Works will exceptionally continue during the night from Friday 23 August until Monday 26 August. Due to the proximity of the works to the intersection with runway 25L/07R, runway 25L/07R will also have to close to air traffic between 11 p.m. on 23 August and 5.30 a.m. on 26 August. This means that during that time, only runway 25R/07L will be in use.

The works are scheduled in such a way as to minimise the impact on the PRS ( Preferential Runway System ) as much as possible. However, it will not always be possible to apply the PRS and delays in operations may occur. 

The selection of runways in use is made by the air traffic services provider skeyes based on runway availability and weather conditions, with the primary aim of ensuring the safety of air navigation.

Runway use, wind conditions, any planned works and their potential impact on runway use are always announced on this website.  

 

Related articles

Overview of additional maintenance works on runway 25L/07R

Works

As announced, Brussels Airport will carry out a second and final phase of maintenance works on runway 25L/07R.

Read more

Additional maintenance works on runway 25L/07R

Works

Following the first phase of maintenance works on runway 25L/07R last June, the second and final phase will take place in November.

Read more

Renovation taxiways INN/OUT 7/8, F3 and Y starts on 16 August

Works

From 16 August to 28 October 2022, the taxiways INN/OUT 7/8, F3 and Y will be undergoing a thorough renovation.

Read more
icon_info Plane departing Group 7 Created with Sketch. Icon triangle warning Icon triangle left Icon triangle right Icon close Icon triangle warning Questionmark Reason meteo Reason obstacles Reason unplanned Reason planned maintenance Reason capacity exceeded Reason unavailable (non-availability) Reason special activities Reason other Search Arrow right